Tuesday, December 20, 2011

12/20/11 Expansion Update

This will probably be the last expansion update before Christmas, but a lot has happened and I wanted to share it with you.

We got confirmation that the tanks are in production at JV Northwest and should be ready in mid- January.  




Nearly all the concrete has been poured for the floor.

The support joists have yet to be cemented into place, though that'll happen soon.

These are by far the largest and most fancy drains in the building.  They've even got strainer baskets to catch debris.

The ceiling lights have been moved over in preparation for the roof  extension.

The brilliant engineers at SL Chasse have found a way to build most of the extension without taking the roof off for a long time.  The crews in the warehouse and bottling line couldn't be happier.


Once the extension is fully assembled, the existing roof structure will be removed while coolant and electric lines out to the space.  That'll make it much easier to "plug and play" when all the tanks arrive form Oregon.

We wish you all a Happy Chanukah and a Merry Christmas!




No comments: